The building schedule
建筑進度表
A: I see there are some workmen on the site When is the building work due to start?
A:我看到在現(xiàn)場有些工人。本建筑工程什么時候開工?
B: Well, it'll take three weeks to demolish the old building and clear away the debris. We should be ready to start the construction work in week 23.
B:哦,需要先用三個星期時間拆除舊建筑并清除廢墟。我們應該在第二十三周開始施工。
A: How long will the sub contractors be on site?
A:承包商多長時間才會到場?
B: About ten weeks in total if everything goes according to plan.
B:如果根據(jù)計劃一切順利,大約共需要十個周的時間。
A: I'm sure it will. So, we should be able to start moving the machinery in during week 34. I'll confirm that date with our suppliers.
A:我確信一定會的。因此,我們應該在第34周中能夠搬運機械設(shè)備。我與我們的供貨商核實一下日期。